Starting around October 22, engineers working for the Big Bear Area Regional Wastewater Agency are spending about a week on the agency's parcel in Erwin Lake. They are doing geophysical surveys, shallow excavations and exploratory drilling at up to 13 spots, as the Big Bear Grizzly reported. The work is for the Greenspot Recharge Project. The agency's plan is to send purified water from its treatment plant into basins on that land, where it would soak down and refill the groundwater the whole Big Bear Valley drinks from.

The drill rigs will help answer where basins could fit on the site. They can't answer whether Greenspot gets built. That depends on a five-member governing board, and the votes that move this project need four of the five. In August, the effort to revive the project's federal loan got three.

What the Crews Are Doing This Week

BBARWA describes the work as part of design, and the agency says it is not construction. Here is the schedule the agency published:

  • About one week of work, starting around October 22
  • Work hours from 8 a.m. to 4 p.m.
  • Up to 13 test locations across the site
  • Every excavation and boring is opened and filled the same day
  • Crews will spray water to keep down dust from digging and vehicles
  • Vehicle noise will come and go through the day, and no significant traffic impacts are expected

"We know local residents have questions about how the basins would be designed and where they would go," BBARWA General Manager David Lawrence said in a news release quoted by the Big Bear Grizzly. "This will give us better data to eventually answer those questions."

This testing may not be the last. Depending on the results, more temporary infiltration testing could happen later this year or in spring 2027, and KBHR 93.3 reported that BBARWA plans to give public notice first.

The Neighborhood Questions This Dig Feeds

BBARWA bought 20 acres in Erwin Lake and proposes basins on roughly seven of them. Which seven is still open. The agency calls this week's testing the way to find "the optimal footprint and placement" for the basins.

That placement question matters to the neighbors. At the September 14 community meeting in Erwin Lake, which drew about 40 people, residents asked about setbacks, views, fencing, landscaping and where facilities would sit on the site. Some suggested moving the project farther from State Lane. Here is how BBARWA's project FAQ answers the most common questions right now:

Question raised in Erwin Lake What BBARWA says now
Where will the basins go, and how many? Not decided. Size, placement, number of basins, landscaping, fencing materials and fence height are all still being defined.
Will there be buildings? No large buildings are expected. Small enclosures may be needed for equipment.
Odor? No perceptible odor is expected, given the water quality and maintenance routines.
Mosquitoes? More insects are possible. The basins would circulate water to avoid stagnant water.
Private wells? Preliminary modeling does not predict harm to private wells. There are currently no plans to monitor them.
Noise? The only steady sound expected is flowing water. Maintenance noise would be scheduled ahead of time.

The land left over after the basins is just as unsettled. The project map labels part of the parcel "Use Not Yet Defined." BBARWA says that label is an early estimate of land it may not need, and the board will decide whether to dispose of any surplus once design is final and the project is funded and built. According to BBARWA's September 28 board packet, the California Department of Housing and Community Development notified the agency that the property qualifies as exempt surplus land, and the next steps wait on the final footprint. At the meeting, some residents asked about parks, trails, athletic fields, BMX facilities or fishing events on that land. Others wanted no public recreation there at all.

Several attendees also said they hadn't heard about the project before the meeting. BBARWA's report lists the outreach it did: about 1,000 emails, signs at the site, social media posts, and door hangers on properties directly facing the parcel. Residents asked for earlier notices and a wider door-to-door radius.

Why Erwin Lake, and What the Rest of the Valley Gets

The site is close to the wells. The Big Bear Lake Department of Water and Power has three Lakewood Wells about half a mile from the parcel, and two of them currently have failed pumping units that could be replaced. Big Bear City Community Services District's Well 2 is about a mile away and near the end of its useful life. Its Well 8a, which came online in 2025, is about two miles away, and so is Well 11, planned for 2028.

BBARWA estimates Greenspot would add 500 acre-feet a year to local groundwater, about what 2,700 average valley households use in a year. The water would move northwest underground. Preliminary modeling puts the trip at about 2 years to the DWP wells and 5 to 8 years to the CSD wells.

The project is also smaller than it used to be. Replenish Big Bear, planned in 2018, once included sending water to Big Bear Lake. In April 2026 the board cut the first phase down to groundwater recharge only, and under Greenspot no water goes to the lake.

Where the Four-Vote Rule Comes In

BBARWA estimates $81.4 million to finish Greenspot, or $88.6 million counting the cost of developing the wider Replenish Big Bear program. The board has to approve the project before construction can start. The agency's financing flyer lists $26.9 million in grants, and the largest single funding source is a $48,999,000 construction loan.

That loan would come through the federal WIFIA program. BBARWA applied in June 2023, and a proposed agreement brought to the board in August 2025 was not approved. The loan has been paused since then. The financing plan presented on August 26, 2026, called for closing the loan "as soon as possible" and holding off on drawing any money until the board approves a construction contract. Approving that contract would also take four votes.

At that August 26 meeting, the general manager told the board the WIFIA loan needs a 4/5 vote. A motion directing staff to bring the loan back for reconsideration and keep pursuing the financing plan failed 3 to 2. A motion to reconsider that vote failed by the same count. Big Bear News reported the deadlock on September 30. The posted agenda for the September 28 special meeting had a Greenspot project report but no loan or financing vote.

So this week's testing can produce a better basin layout, and the board can still decline to fund the project.

The Line on the Sewer Bill

Funding includes sewer rates, and part of the money is already being collected. BBARWA began adding a Replenish Big Bear charge to its rates in FY 2023, paused the increase for FY 2026, and planned to resume it in FY 2027. The agency's September 2026 rate flyer forecasts the established base rate this way:

Fiscal year Established base rate Project portion Increase
FY 2026 $378.20 $96.08 6%
FY 2027 $446.27 $149.88 18%
FY 2028 $526.60 $214.81 18%
FY 2029 $621.39 $294.36 18%
FY 2030 $658.67 $303.19 6%
FY 2031 $685.02 $315.32 4%

These are the agency's established base rates, not a household bill. BBARWA bills its member agencies, including the Big Bear City CSD, based on each one's equivalent dwelling units and three-year average flow, so what lands on a given account varies. Residents at the September meeting raised concerns about bill increases, and one asked specifically about affordability for people on fixed incomes. If you're budgeting for an Erwin Lake or Big Bear City home, treat these figures as general information rather than financial advice, and check your own bill with your water and sewer provider.

Following It From Here

The next regular BBARWA board meeting is Wednesday, October 28, in Big Bear City. The board normally meets on the fourth Wednesday of each month at 5 p.m. As of mid-October, no agenda for that meeting had been posted.

  1. Check the governing board meetings page for the October 28 agenda. Monthly agenda packets also include project spending reports.
  2. Watch for BBARWA notices about follow-up infiltration testing, which could come later this year or next spring.
  3. Read the Greenspot documents page for the environmental review. BBARWA is preparing an addendum to the previously certified Replenish Big Bear environmental impact report.
  4. Send questions to [email protected] or call 909-584-4018.

If you own in Erwin Lake or elsewhere in Big Bear City and want to know where your property stands while Greenspot is still undecided, SoCal Resorts can walk you through it. Get a free home valuation, and we'll keep you posted as the board's decisions come in.

Work With Us

Unlike many of our competitors, we have a full time staff. Our staff members are available seven days a week to help service your home during our listing or buying period. Think of us as your full time concierge during the term of your contract.

Follow Me on Instagram